Assessment of Impact of COVID-19 Lockdown on Nepal’s Construction Sector based on Selected Construction Projects

Authors

  • Priyanka Thapa Department of Civil Engineering, Pulchowk Campus, IOE, TU, Nepal. https://orcid.org/0000-0003-4452-6912
  • Santosh Kumar Shrestha Department of Civil Engineering, Pulchowk Campus, IOE, TU, Nepal.

Keywords:

Construction, Contractual issues, COVID-19, Impact, Lockdown

Abstract

Coronavirus disease 2019 (COVID-19), a global pandemic as declared by World Health Organization (WHO) is causing severe impacts in almost all aspects of life in Nepal. In response to this pandemic, Nepal Government announced a country-wide lockdown from 24th March 2020 and ended on 21st July 2020.
Coronavirus pandemic is an unprecedented event affecting almost every aspect of the construction sector in Nepal. Hence, this study was carried out to assess the impact of COVID-19 lockdown on Nepal’s construction sector based on selected construction projects. For this purpose, a case study of five ongoing construction projects was taken into account and questionnaires were distributed to responsible officials (client, consultant and contractor) of those projects.
This study intended to find out the impact of COVID-19 lockdown on supply-demand trend analysis, cost and time of construction projects. Besides, this study also intends to find the contractual issues and claims associated with COVID-19 lockdown.
The study reveals that COVID-19 caused serious disruption to the supply chain. Subsequently, project cost and time increases due to uncertainty regarding the availability of subcontractors/ suppliers/labour. The impact of COVID-19 lockdown however varies with the nature, scale and size of the project. Besides, the study also implies that contractual disputes are likely to increase due to lockdown. Each contract and its conditions have to be carefully analyzed to determine a party’s specific entitlement.
There is uncertainty as to when the situation becomes normal and construction work can be carried out with optimum efficiency.

How to cite this article:
Thapa P, Shrestha SK. Assessment of Impact of COVID-19 Lockdown on Nepal’s Construction Sector based on Selected Construction Projects. J Adv Res Civil Envi Engr 2021; 8(1): 1-9.

DOI: https://doi.org/10.24321/2393.8307.202101

References

Pradhan T. Government decides to lift the four-monthlong coronavirus lockdown, but with conditions. Retrieved from https://kathmandupost.com/national/2020/07/21/government-decides-to-liftthe-four-month-long-coronavirus-lockdown-but-withconditions.

Ministry of Health and Population. COVID-19 Situation Report. Retrieved from https://covid19.mohp.gov.np/#/

Neupane BR, Mishra AK. Impact of COVID-19 on Labor Management: A Case of Reconstruction Works at Bharatpur Metropolitan City, Nepal. East African Scholars J Econ Bus Manag 2020; 3(10): 28-33. DOI: 10.36349/easjebm.2020.v03i10.004

Dev ER, Mishra AK. Assessment of Casual Labor Management Practices in Construction Projects. Saudi J Bus Manag Stud 2020; 5(9): 482-489. DOI: 10.36348/sjbms.2020.v05i09.001

Mishra AK, Sudarsan JS, Nithiyanantham S. Assessment of time-cost model of public health buildings in Nepal. Asian J Civ Eng 2021; 22: 13-22. https://doi.org/10.1007/s42107-020-00294-4

KPMG. KPMG International. Retrieved from https://assets.kpmg/content/dam/kpmg/sg/pdf/2020/06/Risks-for-construction-Owners.Pdf.

World Health Organization (WHO). Considerations for Public Health and Social Measures in the Workplace in the Context of COVID-19, 1.6. Retrieved from https://www.who.int/publications/i/item/considerations-forpublic-health-and-social-measures-in-the-workplacein-the-context-of-covid-19.

Nepal Law Commission. Infectious Disease Act, 2020 (1964). Retrieved from http://www.lawcommission.

gov.np/en/archives/12240.

Kumar J, Nandhini S, Jeyapriya R. Investigation of Supply Chain Management in Construction Companies. Investigation of Supply Chain Management In Construction Companies 2017; 4(6): 2769-2774. Retrieved from https://www.irjet.net/archives/V4/i6/IRJET-V4I6689.pdf

Ikechukwu AC, Emoh FI, Kelvin OA. Causes and Effects of Cost Overruns in Public Building Construction Projects Delivery, In Imo State, Nigeria. IOSR Journal of Business and Management 2017; 19(7): 13-20. Retrieved from https://doi.org/10.9790/487x-1907021320.

Kumaraswamy MM. Conflicts, claims and disputes in construction. Engineering Construction and Architectural Management 4(2): 95-111. https://doi.org/10.1046/j.1365-232x.1997.00087.x

Mishra AK. Dispute Resolution Practice of Project Management in Nepal. J Adv Res Business Law Tech Management 2018; 1(4): 1-11.

FIDIC. Condition of Contract for Construction for Building and Engineering Works Designed by Employer. Geneva, Switzerland.

FIDIC. Conditions of Contract for Construction For Building And Engineering Works Designed By The Employer (MDB Harmonised ed.). FIDIC.

FIDIC. FIDIC COVID-19 Guidance Memorandum to Users of FIDIC Standard Forms of Works Contract. FIDIC.

Aceris Law. COVID-19 and Construction Disputes: Claims for Time and Money. Https://Www.Acerislaw.Com/Covid-19-and-Construction-Disputes-Claims-for-Timeand-Money/. Retrieved from https://www.acerislaw.com/covid-19-and-construction-disputes-claims-fortime-and-money.

Aryal R, Paudel S, Mishra AK. Impact of Covid-19 on Budget Implementation at Gaindakot Municipality, Nepal. International Journal of Computational Research and Development 2020; 5(2): 1-7.

Belingheri M, Paladino ME, Riva MA. COVID-19: Health prevention and control in non-healthcare settings. Occupational Medicine 2020; 70(2): 82-83. https://doi.org/10.1093/occmed/kqaa048

Central Bureau of Statistics. Trading Economics.Nepal GDP from Construction. Retrieved from https://tradingeconomics.com/nepal/gdp-from-construction.

FCAN. Construction Industry in Nepal. Federation of Contractors Association of Nepal.

Traurig G, Epstein RC, Jensen DC et al. For Developers and Owners: How COVID-19 Is Affecting Construction Projects and Actions You Should Retrieved from https://

www.gtlaw.com/en/insights/2020/4/for-developersand-owners-how-covid19-is-affecting-constructionprojects.

Hai DT. Assessment of Contractorsf Claims on Construction Projects in Vietnam. The Open Civil Engineering Journal 13(1): 218-228. Retrieved from https://doi.org/10.2174/1874149501913010218.

Jergeas GF, Hartman FT. Contractorsf Construction] Claims Avoidance. Journal of Construction Engineering and Management 120(3): 553-560. https://doi.org/10.1061/(asce)0733-9364(1994)120:3(553).

Kartam S. Generic Methodology for Analyzing Delay Claims. Journal of Construction Engineering and Management 125(6): 409-419. https://doi.org/ 10.

/(asce)0733-9364(1999)125:6(409).

Koh D. Occupational risks for COVID-19 infection. Occupational Medicine 2020; 70(1): 82-83. https://doi.org/10.1093/occmed/kqaa036

Kumaraswamy MM. Conflicts, claims and disputes in construction. Engineering Construction and Architectural Management 1997; 4(2): 95-111. https://doi.org/10.1046/j.1365-232x.1997.00087.x

Kumar J, Nandhini S, Jeya PR. Investigation of Supply Chain Management in Construction Companies. Investigation of Supply Chain Management in Construction Companies 4(6): 2769-2774. Retrieved from Https://www.irjet.net/archives/V4/i6/IRJETV4I6689.pdf

Labour Act Nepal (2074).

Ministry of Health and Population. COVID-19 Situation Report. Retrieved from https://covid19.mohp.gov.np/#/

Mishra AK, Aithal PS. Operation of Price Adjustment in ConstructionProjects. International Journal of Case Studies in Business, IT and Education (IJCSBE) 4(2): 229-249. DOI: http://doi.org/10.5281/zenodo.4277033

PPMO. Annual Report of PPMO 2068. Kathmandu.

Pradhan T. Government decides to lift the four-monthlong coronavirus lockdown, but with conditions. Retrieved from https://kathmandupost.com/national/2020/07/21/government-decides-to-liftthe-four-month-long-coronavirus-lockdown-but-withconditions.

Semple C, Hartman FT, Jergeas G. Construction Claims and Disputes: Causes and Cost/Time Overruns. Journal of Construction Engineering and Management 1994; 120(4): 785-795. https://doi.org/10.1061/(asce)0733-9364(1994)120:4(785).

Published

2021-04-13