Study of Inefficiencies in Contract Management Practice in Rural Road

Authors

  • Subash Kumar Bhattarai Visiting Assistant Professor, Construction Project Management, Center for Post Graduate Studies-Nepal Engineering College, Lalitpur, Nepal and Health Infrastructure Policy Development and Procurement Advisor at Nepal Health Sector Support Programme. https://orcid.org/0000-0003-4194-6508
  • Shambhu Kumar Sah Engineer, GoN, NRA, Central Level Project Implementation Unit (GMaLI), Lalitpur, Nepal.

Abstract

The objective of the research is to identify the inefficiencies in contract management practice in the SNRTP sub-projects and also the sources of these inefficiencies will try to find the probable solutions. To study the inefficiencies in contract management practice in SNRTP rural road projects, the checklist was prepared and data regarding the contract management were obtained with the project stakeholders. The data were collected using questionnaires, analysed using SPSS software, MS Excel and presented using the graph, table, and charts. The findings of the study showed that there are significant inefficiencies in contract management practice in the SNRTP project. It has been found that the majority of the respondents i.e. 79 percent of the experts interviewed opined that there are inefficiencies in the contract management practices in the rural road under SNRTP sub-projects, and only 21 percent think that the process is efficient from questionnaire survey. This has been statistically verified through descriptive statistics. The reason behind the inefficiencies in Contract Management Practice is mainly due to a lack of qualifications, knowledge, skills & experience of the contract management team, lack of cooperation & proper communication between project team member, lack of monitoring & evaluation in time, lack of timely meetings, slow decisions making, and improper planning & poor site management during the construction work. To overcome those inefficiencies some suggestions have been recommended as appointing the team member with proper qualifications, knowledge, skills & experience in the contract management. Proper communication & cooperation between team member, frequent inspection, monitoring and evaluation, completion of work within intended completion time, proper record keeping & timely issue management, and timely decision making from all stakeholders as required in construction work during the project implementation phase.

How to cite this article: Sah SK, Bhattarai SK. Study of Inefficiencies in Contract Management Practice in Rural Road. J Adv Res Civil Envi Engr 2021; 8(3&4): 1-8.

DOI: https://doi.org/10.24321/2393.8307.202105

References

Adhikari R, Mishra AK. Strategic Risk Management Practice in Urban Road Construction Project of Nepal. J Adv Res Civil Envi Engr 2020; 7(2): 11-19. https://doi.org/10.24321/2393.8307.202003

Bahadur KCM, Mishra AK. Bidding Trends of Contracts based on Types and Sizes of Projects under Road Divisions Butwal and Shivapur. J Adv Res Const Urban Arch 2019; 4(3&4): 7-16. https://doi.org/10.24321/2456.9925.201905

DoLIDAR. Project Operation Manual (Version-2). Project for Strengthening the National Rural Transport Program (SNRTP). Available from: http://snrtp.gov.np/snrtp/wp-content/uploads/2016/07/SNRTP-Revised-POMApproved-on-14-April.pdf. Accessed on August 2, 2018.

Mishra AK, Mishra S. Assessment of Group Formation for Output-Based Routine Road Maintenance Approach in Surkhet District, Nepal. J Adv Res Civil Envi Engr 2018; 5(3): 1-8 . https://doi.org/10.24321/2393.8307.201801.

Mishra AK. Project Management: Theory And Practice From Different Countries. Project Management: Theory And Practice From Different Countries. Tamilnadu: DK International Research Foundation. 2020; 345. http://doi.org/10.5281/zenodo.4817542

Mishra AK, Bhandari S. Performance Assessment of ongoing Construction projects under Town Development Fund, Nepal. Int J Adv Res Civil Stru Engr 2018; 1(1&2): 27-39.

Macro S. Effectiveness in contract management in Tanzania, A case study of Tanroads. 2013.

National Planning Commission. 14th National Plan. Nepal: NPC. 2017.

Public Procurement Act 2063 & Public Procurement Rule 2064. Available from: https://ppmo.gov.np/image/data/files/acts_and_regulations/public_procurement_act_2063.pdf;https://ppmo.gov.np/image/data/files/acts_and_regulations/public_procurement_rules_2064.pdf.

Sarkar PP. Contract management practice for the procurement of goods in the public sector in Bangladesh (A case study of LGED). Master’s thesis, BRAC Institute of Governance and Development, BRAC University. 2015.

Standard Bidding Document used for Upgrading of Road under SNRTP Sub-Projects (Approved by World Bank). National Rural Roads Development, Agency Ministry of Rural Development, Government of India.

Statistics of Local Road Network (SLRN). Department of Local Infrastructure Development and Agricultural Roads (DoLIDAR), 2016.

Thakur M, Mishra AK. Effectiveness of Technical Audit Practice: A Case of Parsa District of Nepal. NOLEGEIN Journal of Operations Research & Management 2020; 3(2): 8-36p. 10.37591/njorm.v3i2.558

Published

2021-09-22