Variations Order of Building Construction Project: A Case from Nepal

Authors

  • Neetu Koirala Master Research Scholar, Madan Bhandari Memorial Academy Nepal, Urlabari 3, Morang, Nepal. https://orcid.org/0000-0001-8166-2206
  • Prakash Sharma Master Research Scholar, Madan Bhandari Memorial Academy Nepal, Urlabari 3, Morang, Nepal.
  • Laxmi Prasad Sapkota Master Research Scholar, Madan Bhandari Memorial Academy Nepal, Urlabari 3, Morang, Nepal.
  • Mina Yogi Master Research Scholar, Madan Bhandari Memorial Academy Nepal, Urlabari 3, Morang, Nepal.
  • Anubhav Pokharel Master Research Scholar, Madan Bhandari Memorial Academy Nepal, Urlabari 3, Morang, Nepal.
  • Hemant Gain Master Research Scholar, Madan Bhandari Memorial Academy Nepal, Urlabari 3, Morang, Nepal.

Keywords:

Variation, Design, Delay, Client, Consultant, Dispute

Abstract

The main objective of this study is to identify the origin and causes of variation orders and their impacts in project cost and completion time for developing preventing measures which can be beneficial in upcoming similar projects. The study is conducted in project inside the
Tribhuvan University premises, Kathmandu. The primary data were collected from the questionnaire survey and field study. A questionnaire survey was conducted with construction team who are related to the project. For the case study of the project, contract documents were obtained from the related offices which were thoroughly studied to
obtain the project related findings about variation orders relating to project cost and completion time. Five ranking linkert scale have been used for ranking the perception based relative importance index of respondents about causes of variation orders. Existence of variation orders inside Tribhuvan University premises, Kathmandu has been noted from the study. 9.85%, 5.99%, 10.37%, 12.32% and 21.02% cost above the contract amount has been incurred at the completion of the projects respectively. Similarly, 26.67%, 83.33%, 12.5%, 20% and 25% time for the successive contract has been increased by the extension of the contract completion time. From the study, main causes of variation orders are known to be change of plan, change of scope, defect of bill of quantities, lack of specified and appropriate competent construction manager and impediment in prompt decision making. Similarly, causes of variation orders impacting project cost are additional work, client financial problems/ delay in payment of bill and change in design. Causes of variation orders impacting project time are change in design, delay in payment and dispute between parties to the contract. The control measures for the variation orders are appointment of project manager to supervise design, preparation of bill of quantities with good estimate and adequate financial planning. The findings of this study will be beneficial for developers, designers and contractors in building
projects and also to the Governmental authorities to develop preventing measures to eliminate or reduce variation orders.

How to cite this article: Koirala N, Sharma P, Sapkota LK et al. Variations Order of Building Construction Project a Case from Nepal. J Adv Res Const Urban Arch 2021; 6(2): 25-33.

DOI: https://doi.org/10.24321/2456.9925.202105

References

Faisal A, Low P. The potential effects of variation orders on institutional building projects. Facilities 2005; 23(11&12): 496-510.

Al-Hakim L. Waste identification: a supply chain strategy perspective. International Conference on Business and Information, Hong Kong. 2005. Available from: https://

eprints.usq.edu.au/archive/00000207/01/2005bai180.pdf.

Bower DA systematic approach to the evaluation of indirect costs of contract variations. Construction Management and Economics 2000; 18(3): 263-268.

Lbbs CW. Quantitative impacts of project change: size issues. Journal of Construction Engineering and Management 1997; 123(3): 308-311.

Chan APC, Yeong CM. A Comparison of Strategies for Reducing Variations. Construction Management and Economics 1995; 13(6): 467-73.

Charoenngam C, Coquinco ST, Hadikusumo BHW. Web-based application for managing change orders in construction projects. Construction Innovation 2003; 3: 197-215.

FIDIC 1999. Conditions of contract for construction, for building and engineering works designed by the employer (Multilateral Development Bank Harmonized Edition). International Federation of Consulting Engineers (FIDIC)., Geneva, Switzerland. 2010.

Finsen E. The building contract - a commentary on the JBCC agreements. 2nd ed. Juta & Co. Ltd., Kenwyn. 2005.

Formoso TC, Isatto EL, Hirota EH. Method for waste control in the building industry. University of California, Berkeley, USA. 1999; 325-334.

Hanna ASPE, Calmic R, Peterson PA et al. Quantitative definition of projects impacted by change orders. Journal of Construction Engineering and Management 2002; 128(1): 57-64.

Harbans SKS. Valuation of varied work: a commentary. In: Bulletin Ingénieur. The Board of Engineers Malaysia 2003; 20(3): 32-42.

Hillebrandt P. Analysis of the British Construction Industry, Macmillan, London. 1985.

Mishra AK. Dispute resolution practice of project management in Nepal. J Adv Res Busi Law Tech Mgmt. 2018; 1(4): 1-11.

Mishra AK, Mandal L, Pant RR. Causes of dispute in international competitive bidding road contracts funded by Asian development bank in Nepal. J Adv Res Busi Law Tech Mgmt. 2018; 1(3): 5-16.

Mishra AK, Sudarshan JS, Nithiyanantham S. Assessment of time-cost model of public health building in Nepal. Asian J Civ Eng., 2020. DOI: https://doi.org/10.1007/

s42107-020-00294-4

Mishra AK, Aithal PS. Financial impact assessment of time overrun: a case of second small towns water supply and sanitation sector project, Nepal. International Journal of Applied Engineering and Management Letters 2020; 4(2): 159-73. DOI: http://doi.org/10.5281/

zenodo.4074715

Mishra AK, Aithal PS. Operation of price adjustment in construction projects. International Journal of Case Studies in Business, IT, and Education 2020; 4(2): 229- 49. DOI: https://dx.doi.org/10.2139/ssrn.3732323

Mishra A, Regmi U. Effects of price fluctuation on the financial capacity of “Class A” contractors. International Journal of Creative Research Thoughts 2017; 5(4): 1920-1938.

Mishra AK, Shrestha M. Health and safety status of casual workers in road improvement project Kathmandu Valley, Nepal. International Journal of Engineering Technology Science and Research 2017; 4(9): 1187-1199.

Mishra AK. Global Contract Administration. Global Contract Administration, Tamilnadu: DK International Research Foundation. 2020; 145. http://doi.org/10.5281/zenodo.4817527

Mishra AK. Project Management: Theory and Practice From Different Countries. Project Management: Theory And Practice From Different Countries. Tamilnadu: DK International Research Foundation. 2020; 345. http://doi.org/10.5281/zenodo.4817542

Mishra AK. Implementation Status of Value Management in Project Management Practice in Nepal. International Journal of Management Studies 2019; 6(1). 92-108. DOI: 10.18843/ijms/v6i1(1)/13.

Ruben N. An analysis of the impact of variation orders on project performance. M.T.C.M. Cape Peninsula University of Technology. 2008.

Koskela L, Vrijhoel R. The Prevalent Theory of Construction is Hindrance for Innovation. In: IGLC-6 (International Group for Lean Construction). Eighth Annual Conference of the International Group for Lean Construction, Brighton, UK, 2000. Retrieved July 10, 2018, from https://www.leanconstruction.org/pdf/25.pdf.

Wainwright WH. Wood AAB. Variation and Final Account Procedure. 4th ed. London: Hutchinson. 1983.

Uyun NMY. Variation Control Affecting Construction Works for Lembaga Kemajuan Tanah Persekutuan (Felda). Thesis. University of Technology, Malaysia. 2007.

Levy SM. Project Management in Construction. 4th Ed. Columbus: McGraw-Hill. 2002.

Love PED, Li H. Quantifying the Causes and Costs of Rework in Construction. Construction Management and Economics 2000; 18: 479-490.

Hanna ASPE, Calmic R, Peterson PA et al. Quantitative Definition of Projects Impacted by Change Orders. Journal of Construction Engineering and Management 2002; 128(1): 57-64.

Published

2021-07-13