Price Adjustment Practice of Road Projects in Nepal

Authors

  • Sagar Pokharel Master's Scholar, Lumbini Engineering and Management Science College, Rupandehi, Nepal.
  • Anjay Kumar Mishra Visiting Professor, Lumbini Engineering and Management Science College, Rupandehi, Nepal. https://orcid.org/0000-0003-2803-4918

Abstract

The construction industry always faces problems on price fluctuation and adjustment of the price to compensate the cost fluctuation becomes necessary. There is dilemma on which formula of price adjustment to use in construction contracts. Price adjustment affects all the stakeholders i.e. Client, Consultant and Contractor. This research revealed about the trend of the cost of components of construction i.e. Labor, Material, Fuel, equipment etc. Compare the different formulas of price adjustment and understand the view of client, Consultant and Contractor regarding price adjustment.
Questionnaire was distributed to the Client, Contractor and consultant’s representative who are a part of the above projects. For the questions based on Likert scale, afive point Likert scale ranging from 1 to 5 is adopted and Relative Importance Index wascalculated and for other questions the result is presented in the form of pie chart and bar chart.
From our study, it can be concluded that most of the Clients, Contractors and Consultants are affected by price adjustment. PPMO formula should be used for price adjustments in construction contracts.After the initial completion date of contract has crossed and extension of time has been done, the price adjustment factor should be calculated based on the indices before and upto the initial completion date only and Price adjustment should be provided after the initial completion date of contract also. The research findings also suggest that 25% of bidders bid for the value range of 0-5% below the Engineers’ Estimate while only 13.85% of bidders in case of E-bidding bid for the same range.
The researcher believes that the findings of this study are useful for reviewing the existing provision of public procurement system. This also supports the conviction that more constructive roles has to be played in public procurement of infrastructure projects by local governments in Newly Constituted Federal Structure of Nepal.

How to cite this article:
Pokharel S, Mishra AK. Price Adjustment Practice of Road Projects in Nepal. J Adv Res Const Urban Arch 2020; 5(3&4): 20-31.

DOI: https://doi.org/10.24321/2456.9925.202003

References

ADB. Price Adjustment Guidance Note on procurement. 2018.

Atkenson A. Civil Engineering Contract Administration. Trans-Atlantic Publication. 1992.

Barthet P, Wasserstein D. The 3 p’s of price adjustment clauses. 2010.

Castillo J, Al-jibouri S, Halman J. Risk based design making in construction: a case of planning and risk assesment of construction alternatives. 2009.

De Vynck D. The Use of Haylett in a Low Inflation Environment. 2002.

Dinku A. Construction management and finance. AAU Printing press. 2003.

DOR. Department of Road Bussiness plan. 2012.

FIDIC MDB. Conditions of Contract for Construction. Multilateral Development Bank Harmonised Edition. General conditions. 2010.

Finsen E. The Building Contract. A commentary on the JBCC Agreement. 2005.

Flyrberg B. Policy and Planning of large Infrastructure Project Problems, Causes, Cures. World Bank Policy Research paper 3781, 2005.

Highways Term maintenance Association (HTMA). Price Adjustment Formula Indices (Highway Maintenance) 2010-Series-Guidance Notes. Prepared in asociation with the Civil Engineering Contractor’s Association and Building Cost Information Service. 2010.

Hong Kong Bureau of Development. Note for Finance Committee- Application of Contract Price fluctauation, 2008.

Institute for the Construction Training and Development (ICTAD). Sri Lanka Country Report. The 14th Asia Construct Conference. 2008.

Institute of Civil Engineers. Engineering and Construction Contract: Guidance note. Second edition. Thomas Telford, London. 1995.

J.E.A, C., S.H.S, A.-J, JIM H. Risk-based decision making in construction: a case of planning and risk assesment of construction alternatives. 2009.

Kinala D, Roukema D. When is an escalation necessary? Dealing with price flucturation in dredging contracts. 2011.

Koirala. Price Adjustment Contract Administration in Nepalese Construction Contracts (Road). 2019.

Kosmopoulouy GZ. Price Adjustment Policies in Procurement contracting. 2011.

MC Cartney M. Pakistan, Growth, Dependency and crisis. The Lahore Journal of Economics 2011; 16: 71-94.

Mishra AK. Regmi U. Effects of Price Fluctuation on the Financial Capacity of “Class A” Contractors. International Journal of Creative Research Thoughts (IJCRT) 2017. www.ijcrt.org.

Mishra AK, Aithal PS. Operation of Price Adjustment in Construction Projects. International Journal of Case Studies in Business, IT, and Education (IJCSBE) 2020; 4(2), 229-249. DOI: http://doi.org/10.5281/zenodo.

Mossa. Assessment of Price Escalation and Adjustment Problems on Federal Road Construction Projects. 2013.

MOF. Economic Survey. 2018.

National Highway Authority of India (NHAI). NHAI Works Manual. 2006.

Newnon D, Lavelle J, Eschenbach T. Engineering economic analysis. 2002; 8.

Public procurement regulation. (2064). schedule 1 method of calculating cost estimates. Nepal: Public procurement monitioring office, Nepal government.

Queensland Department of Main Roads. Road Construction Contract Supplementary Conditions of Contract,User guide, No. C6838. 2005.

Riggs J. Material price escalation. Construction briefing. 2006.

Saunders M, Lewis P, Thornhill A. Research methods for Business students. London: Practice Hall. 2007.

Trickery G. The Presentation and Settlement of Contractor’s claims. London: E & F.N. 1983.

Tripathi A. New business age. 2015. Retrieved fromhttp://www.newbusinessage.com: http://www.newbusinessage.com/MagazineArticles/view/1250

U.S Department of Transportation. Development and Use of Price Adjustment Contract Provisions. Federal Highway Administration Technical Advisor Number. 1980; 158.

Mishra AK, Singh NK. Bidders’ Competitiveness in Rural Road Projects in Nepal: A Case Study of World Bank Funded Project, Solid State Technology. 2019; 62(1). http://www.solidstatetechnology.us/index.php/JSST/issue/view/9

Published

2021-10-19

Most read articles by the same author(s)

1 2 > >>