A Review on Time and Cost Issues of Infrastructure Projects
Abstract
The research is a review research conducted on the issues of time and cost performance of infrastructure projects in global and local context using content analysis. Time extension is a serious issue and further research for specific project should be conducted to search the effective measures in the area. During project based study the quality part should be assured as time and cost may be affected by or can affect quality of the project. The review has highlighted several factors affecting time overrun and cost overrun along with the relation between the same. Time, Cost and Quality are three sides of a project performance triangle. Project is one time unique process with specific objective which is source of innovation and
development. Time extension is not an exception but norms for infrastructure projects should be verified through ecological testing and possible measures should be strongly enforced for systematic performance improvements of projects. The study will be significant for policy maker and professional project managers working in the sector of infrastructure development projects.
How to cite this article: Mishra AK. A Review on Time and Cost Issues of Infrastructure Projects. J Adv Res Const Urban Arch 2018; 3(1&2): 32-46.
DOI: https://doi.org/10.24321/2456.9925.201807
References
Adenuga OA. Factors Affecting Quality in the Delivery of Public Housing Projects in Lagos State, Nigeria. International Journal of Engineering and Technology 2013; 3.
Adenuga OA., n.d.
Enshassi A. S. M. S. A. Factors Affecting the Performance of Construction Projects in the Gaza Strip. Journal of Civil Engineering and Management 2009; 15: 269-280.
Ahmed S, Azher S, Castillo M et al. Construction delays in Florida; an empirical study. [Online] Available at:
Aibinu AA, Jagboro GO. The effects of construction delays on project delivery in Nigerian construction industry. International Journal of Project Management 2002; 20: 593-599.
Alexander TY. Assessment of Cost and Time Impacts of Public Sector Construction Projects in Ghana. MBA. Kwame Nkrumah University of Science and Technology. 2011.
Alfred L. Construction Productivity. New York: MC Graw Hill. Anon., n.d. 1998.
Ameh OJ, Osegbo EE. Study of relationship between time overrun and productivity on construction sites. International Journal of Construction Supply Chain Management 2011; 1(1): 56-67.
Apolot R, Alinaitwe H, Tindiwensi D. An Investigation into the Causes of Delay and Cost Overrun in Uganda’s Public Sector Construction Projects. Second International Conference on Advances in Engineering and Technology. [Online] Available at: [Accessed 17 March, 2014]
Arcila SG. Avoiding Cost Overruns in Construction Projects in the United Kingdom. M Sc. The University of Warwick. 2012.
Arditi D. A. G. M. Total quality management in the construction process. 1998.
Assaf SA, Al-Hejji S. Causes of delay in large construction projects. International journal of project management. 2006; 24(4): 349-357.
Assessment (ESSA, s.l.: s.n).
Available at: www.dolidar.gov.np
Available at: www.dolidar.gov.np
Available at: www.dor.gov.np
Azhar N, Faroouqi RU. Cost Overrun Factors In Construction Industry of Pakistan. First International Conference on Construction in Developing Countries (ICCIDC–I). Advancing and Integrating Construction Education, Research & Practice. Karachi, Pakistan. 2008.
Baker RD. Time and Cost Correlation in Construction. 1991.
Bank W. Bridge Development Program: Environment and Social Systems. 2012.
Bromilow FJ, Hinds MF, Moody NF. Australian Institute of Quantity Surveyors: survey of building contract time performance. The Building Economist 1980; 79-82.
Bromilow FJ. Measurement and Scheduling of Construction Time and Cost Performance in the Building Industry.The Chartered Builder 1974; 10(9): 57-65.
Central Bureau of Statistics (CBS). Major Highlights of Census 2011. [Online] Kathmandu: CBS. Available at: <http://cbs.gov.np/wp-content/uploads/2012/11/Major-Finding.pdf> [Accessed 3 August 2013]
Chan DWM, Kumaraswamy MM. Compressing Construction Durations: Lessons Learned from Hong Kong Building Projects.Internation Journal of Project Management 2002; 20 (2002): PP 23-35
Choudhury I, Rajan SS. Time - Cost Repationship for Residential Construction in Texas. [Online] Available at: <https://www.cs.auckland.ac.nz/research/conferences/w78/.../W78-24.pdf> [Accessed at 25 July, 2014]
Congress TIR. Guidelins on Quality Systems for Road Bridges. New Delhi, s.n. DoLIDAR, 2012. Annual Progress Report, Kathmandu: s.n. 1998.
Department of Roads (DoR). Nepal Bridge Standards-2067. Kathmandu: DoR. 2010.
Department of Roads (DoR). Road Projects. [Online] Available at: <http://www.dor.gov.np/ road_ projects. php> [Accessed 13 May 2014]
DoLIDAR. Yearly Progress Report for FY: 2070/71. Kathmandu, Nepal: Department of Local Infrastructure Development and Agricultural Roads DoLIDAR, n.d. [Online]. 2014.
DOR M. Standard Specification for Road and Bridge works. s.l., s.n. DOR, n.d. [Online]. 2014.
Durdyev S, Ismail S, Bakar NA. Factors Causing Cost Overruns in Construction of Residential Projects; Case Study of Turkey. International Journal of Science and Management 2012; 1(1): 3-12.
Ekantipur, n.d. 80-metre under-construction bridge collapses in Kabilas. [Online] Available at: http://kathmandupost.ekantipur.com/printedition/news/2014-05-26/80-metre-under-constructionbridge-collapses-in-kabilas.html
Facility AI. Construction Quality Assurance/Quality Control Plan - Groundwater Source Control Measure, Portland, Oregon: s.n. 2011.
FIDIC. Conditions of Contract for Construction, For Building and Engineering Works Designed By the Employer (Multilateral Development Bank Harmonized Edition). Geneva, Switzerland: International Federation of Consulting Engineers (FIDIC). 2010.
Flyvbjerg B, Holm MKS, Buhl SL. What Causes Cost Overrun in Transport Infrastructure Projects? [Online] Available at: <http://flyvbjerg.plan.aau.dk/COSTCAUSESASPUBLISHED.pdf> [Accessed 14 Sep 2014]
GoN, 2063. Public Procurement Act. s.l., s.n.
GoN, 2064. Public Procurement Regulation. s.l., s.n. HMG/Nepal, 2002. Public Work Directives. s.l., s.n.
Haseeb M, Lu X, Bibi A et al. Causes and Effects of Delays in Large Construction Projects of Pakistan. [Online] Available at: <http://www.arabianjbmr.com/VOL_1 _(4)_KD.php> [Accessed: 5 September 2013]
International Journal of Construction Engineering and Management, 3: 65.
Internetional Journal of Project Management, Volume 15, pp. 235-243.
IYER, KNJ. &. KC. Critical Factors Affecting Quality. 2006.
Joshi U. D., 2003. Management Issues in the Early Stages of a Project that lead to Delay in Implementation: A Case Study of Melamchi Water Supply Project.M Sc. Pokhara University.
Justin Fischgrund, V. O., 2014. Quality in Construction: Identifying the Gaps.
Kanji, G. &. W. A., 1998. Quality Culture in Construction Industry. s.l.:s.n. Kanji, G. &. W. A., 1998. Quality Management in Construction Industry. s.l.:s.n. Kothari, 2004. Research Methodology, s.l.: New Age International.
Kikwasi G. J., 2012. Causes and effects of delays and disruptions in construction projects in Tanzania. [Online] Available at: <http://epress.lib.uts.edu.au/journals/index.php/AJCEB-Conference-Series/article/view/3166> [Accessed: 5 September 2013.
Kothari C. R. and Garg G., 2014.Research Methodology - Methods and Techniques.Third Edition. New Delhi, India: New Age International (P) Limited. 46. Kothari C. R., 2004. Research Methodology - Methods and Techniques.Second Edition. New Delhi, India: New Age International (P) Limited.
LRBPNepal, n.d. [Online] Available at: www.lrbpnepal.org [Accessed 21 June 2016].
Mahamid I. and Amund B., 2012. Cost deviation in road construction projects: the case of Palestine. Australasian Journal of Construction Economics and Building.Vol. 12 (1). PP 58-71
Mahamid I., 2013. Frequency of time overrun causes in road construction in Palestine: Contractors’ View. Organization, Technology and Management in Construction: an International Journal.Vol. 5 (1). PP720-729.
Mak M. Y., Ng S. T., Chen S. E. and Varnam M., 2000. The relationship betweeCSJMUonomic indicators and Bromilow’s time-cost model: a pilot study. 16th Annual ARCOM Conference, Association of Researchers in Construction Management.6-8 September 2000, Glasgow Caledonian University, Akintoye, Vol. 2, PP 587-95.
Mears, P., 1995. Quality Improvement Tools and Technique. New York: McGraw Hill. Nepal, G. o., 2067. Nepal Bridge Standards. s.l., s.n.
Melamchi Water Supply Project (MWSP), 2014. Project Progress Report. [Online] Available at: <http://www.melamchiwater.org/status/progress-report.php> [Accessed 25 February 2014]
Memon AH, Rahman IA, Abdullah MR et al. 2010. Effects of Construction delay in Large Construction projects: Project Management Consultants Perception. [Online] Available at <http://www.academia.edu/2487617/Proceeding_of_CoGIS2010_Conference_on_Postgraduates_IncentiveResearch_Grant> [Accessed: 5 September 2013]
Memon AH, Rahman IA, Abdullah MR et al. Factors Affecting Construction Cost Performance in Project Management Projects: Case of MARA Large Projects. 2011.
Memon AH, Rahman IA, Abdullah MR et al. Time and Cost Perfomance in Costruction Projects in Southern and Cenrtal Regions of Penisular Malaysia. International Journal of Advances in Applied Sciences (IJAAS). 2012; 1(1): 45-52.
Ministry of Agricultural Development (MoAD), 2013. Welcome to Ministry of Agricultural Development. [Online] Available at: <http://www.moad.gov.np/>[Accessed 6 August 2013]
Nega F., 2008. Causes and Effects of Cost Overrun on Public Building Projects in Ethiopia. M. Sc. Thesis, Addis Ababa University.
Nepal Electricity Authority (NEA), 2013.A Year in Review: Fiscal Year 2012/13. Kathmandu: NEA
Nyabwari, N. E., 2012. An Investigation on the Causes and Effects of Cost Overrun on Civil Works Projects in Mombasa County.MBA Thesis, Kenyatta University.
Oakland, J. a. A. A., 1995. Quality management in civil and structural engineering consulting. International Journal of Quality and Reliability Management.
Odabasi, E., 2009. Models for Estimating Construction Duration: An Application for Selected Buildings on the METU Campus.M. Sc. Thesis, Middle East Technical University.
Olusegun A. Abandonment of construction projects in Nigeria. Journal of Emerging Trends in Economics and Management Science 2011; 2: 142-145.
Performance in Construction Projects. s.l.:s.n.
PPA, 2007. Public Procurement Act. Kathmandu, Nepal: Nepal Law Commission. 2007.
PPMO. Standard Bid Document for Procurement of Works for above 6 Million Rupees (NCB). [Online] Available at: Accessed 11 April, 2014]
PPR, 2007. Public Procurement Rules - 2007. Kathmandu, Nepal: Nepal Law Commission. Project. 2007.
Quality Culture in the Construction Industry.
Regmee P. Quality Control Measures Adopted by Supervision Consultant of Road. 2010.
RRRSDP. About the Project. 2010. [Online] Available at: <http://rrr.gov.np/about-project-intro-description.php> [Accessed 1 March 2013]
Salunkhe AA, Patil RS. Effect of Construction Delays on Project Time Overrun: Indian Scenario. International Journal of Research in Engineering and Technology.
[Online] Available at: <http://www.ijret.org> [Accessed 12 June 2014]
Sambasivan M, Soon YW. Causes and Effects of Delays in Malaysian Construction Industry. International Journal of Project Managemen 2006. [Online] Available at: <http://www.iiste.org/Journals/index.php/IEL/article/view/4275/4344>
Shr JF, Chen WT. Functional Model of Cost and Time for Highway Construction Projects.Journal of Marine Science and Technology 2006; 14(3): 127-138.
Singh R., 2009. Cost and Time Overruns in Infrastructure Projects: Extent, Causes and Remedies. [Online] Available at: <http://www.econdse.org/faculty/ram/ram.htm> [Accessed 15 July, 2014]
Singh YK. Fundamentals of Research Methodology and Statistics. New Delhi, India: New Age International (P) Ltd. 2009.
Sthapit A. B., Gautam H., Joshi P. R. and Dangol P. M., 2010.Statistical Methods.Fifth Edition. Kathmandu, Nepal: Buddha Academic Publishers and Distributors Pvt. Ltd.
Tumi, S. A. H., Omran, A. and Pakir, A. H. K., 2009. Causes of Delays in Construction Industry in Libya. The International Conference on Economics and Administration, Faculty of Administration and Business, University of Bucharest. Bucharest, Romania. 14-15th November 2009.
Vidalis S. M. and Najafi F. T., 2002.Cost and Time Overruns in Highway Construction. Canada, June 2002. Montreal: Canadian Society for Civil Engineers.
Wan Yusoff Wan Mahmood, A. H. M. M. S. M. Z. M. Y. A. B., 2006. Development of
Willar D. Improving quality management system implementation in Indonesian construction companies. 2012.